Boise Airport's Capital Improvement Plan

In order to meet the demand of the travelling public, the Boise Airport will begin a multi-year capital improvement plan to increase capacity for a number of items. Projects include parking structures for passengers and employees, rental car lobby and garage, a new concourse, and various other supporting projects.

The airport will update this page regularly with details related to each project.

Contractors can view a list of all open bids by the city of Boise here.

Graphic rendering of BOI Upgrade Projects

Project Details

Employee Parking Garage

This project consists of design and construction of a five-level, 716 stall, open garage with interior ramps, non-sprinklered, no roof, occupancy group S-2, type IB, cast in place, post tension construction. Project includes utility relocation, minor road construction, and landscaping.

Graphic Renderings & Site Plan

Design Team: TO Engineers, CSHQA, Walker Parking

Construction Bid: The preliminary timeline to advertise, open and award this bid is Fall/Winter 2019

Employee Parking Garage highlighted in green

Public Parking Garage Expansion

This project consists of preliminary design and design/build construction of a four-level, 800~ stall, open garage, with metal roof, exterior ramps, non-sprinklered, occupancy group S-2, type IB, cast in place, post tension construction. Project includes utility relocation, minor road construction, and landscaping. 

Conceptual Design Team: RS&H, WH Pacific, Terracon

Design TeamThe preliminary timeline to advertise, open and award this bid is late 2019/early 2020

Construction BidThe preliminary timeline to advertise, open and award this bid is late 2019/early 2020

Public Parking Garage highlighted in green

Rental Car Garage and Lobby

This project consists of conceptual design, design, and construction of a six-level, 1000~ stall, open garage with exterior ramps, non-sprinklered, no roof, occupancy group S-2, type IB, cast in place, post tension construction. Project also includes design and construction of an approximate 36,000 SqFt two-level customer lobby and rental car office with connecting walkway, restrooms and elevators. Project also includes utility relocation, minor road construction, fencing, and landscaping. 

Planning, Conceptual Design Team: RS&H

Design BidThe preliminary timeline to advertise, open and award this bid is Fall/Winter 2019

Construction BidThe preliminary timeline to advertise, open and award this bid is Summer/Fall 2020

Rental Car Garage highlighted in green

Concourse A Apron

This project consists of conceptual design, design, and construction of approximately 250,000 SqFt of 15” concrete apron. 

Design Team: RS&H, TO Engineers

Construction BidThe preliminary timeline to advertise, open and award this bid is Summer 2020

Concourse A Apron highlighted in green

Concourse A

This project consists of conceptual design, design, and construction of a two-level, approximate 44,000 SqFt concourse, walkway, retail space, and offices. Project also includes passenger boarding bridges, furniture, moving sidewalks, fencing, and apron. 

Conceptual Design Team: RS&H

Design BidThe preliminary timeline to advertise, open and award this bid is Spring/Summer 2020

Construction BidThe preliminary timeline to advertise, open and award this bid is currently undetermined